Industrial Engineering
61. Motion study involves analysis of
- actions of operator
- layout of work place
- tooling and equipment
- all of the above
- none of the above.
Correct answer: (A)
actions of operator
62. One of the basic essentials of an incentive plan is that
- a differential piece rate system should exist
- minimum wages should be guaranteed
- provide incentive to group efficiency performance
- all standards should be based on optimum standards of production
- all standards should be based on time studies.
Correct answer: (E)
all standards should be based on time studies.
63. One time measurement unit(TMU) in method time measurement system equals
- 0.0001 minute
- 0.0006 minute
- 0.006 minute
- 0.001 minute
- 0.06 minute.
Correct answer: (B)
0.0006 minute
64. Per cent idle time for men or machines is found by
- work sampling
- time study
- method study
- work study
- ABC analysis.
Correct answer: (A)
work sampling
65. PERT and CPM are
- techniques to determine project status
- decision making techniques
- charts which increase aesthetic ap-pearance of rooms
- aids to determine cost implications of project
- aids to the decision maker.
Correct answer: (E)
aids to the decision maker.
66. PERT has following time estimate
- one time estimate
- two time estimate
- three time estimate
- four time estimate
- nil time estimate.
Correct answer: (C)
three time estimate
67. PERT is the
- time oriented technique
- event oriented technique
- activity oriented technique
- target oriented technique
- work oriented technique.
Correct answer: (B)
event oriented technique
68. Pick up the incorrect statement about advantages of work sampling
- permits a fine breakdown of activities and delays
- simultaneous study of many operators may be made by a single observer
- calculations are easier, method is economical and less time consuming
- no time measuring devices are generally needed
- as operators are not watched for long periods, chances of obtaining misleading results are less.
Correct answer: (A)
permits a fine breakdown of activities and delays
69. PMTP (predetermined motion time systems) include
- MTM (method time measurement)
- WFS (work factor systems)
- BNTS (basic motion time study)
- all of the above
- none of the abbvev
Correct answer: (D)
all of the above
70. Process layout is employed for
- batch production
- continuous type of product
- effective utilisation of machines
- all of the above
- none of the above.
Correct answer: (A)
batch production