Industrial Engineering

61. Motion study involves analysis of

  1. actions of operator
  2. layout of work place
  3. tooling and equipment
  4. all of the above
  5. none of the above.

Correct answer: (A)
actions of operator

62. One of the basic essentials of an incentive plan is that

  1. a differential piece rate system should exist
  2. minimum wages should be guaranteed
  3. provide incentive to group efficiency performance
  4. all standards should be based on optimum standards of production
  5. all standards should be based on time studies.

Correct answer: (E)
all standards should be based on time studies.

63. One time measurement unit(TMU) in method time measurement system equals

  1. 0.0001 minute
  2. 0.0006 minute
  3. 0.006 minute
  4. 0.001 minute
  5. 0.06 minute.

Correct answer: (B)
0.0006 minute

64. Per cent idle time for men or machines is found by

  1. work sampling
  2. time study
  3. method study
  4. work study
  5. ABC analysis.

Correct answer: (A)
work sampling

65. PERT and CPM are

  1. techniques to determine project status
  2. decision making techniques
  3. charts which increase aesthetic ap-pearance of rooms
  4. aids to determine cost implications of project
  5. aids to the decision maker.

Correct answer: (E)
aids to the decision maker.

66. PERT has following time estimate

  1. one time estimate
  2. two time estimate
  3. three time estimate
  4. four time estimate
  5. nil time estimate.

Correct answer: (C)
three time estimate

67. PERT is the

  1. time oriented technique
  2. event oriented technique
  3. activity oriented technique
  4. target oriented technique
  5. work oriented technique.

Correct answer: (B)
event oriented technique

68. Pick up the incorrect statement about advantages of work sampling

  1. permits a fine breakdown of activities and delays
  2. simultaneous study of many operators may be made by a single observer
  3. calculations are easier, method is economical and less time consuming
  4. no time measuring devices are generally needed
  5. as operators are not watched for long periods, chances of obtaining misleading results are less.

Correct answer: (A)
permits a fine breakdown of activities and delays

69. PMTP (predetermined motion time systems) include

  1. MTM (method time measurement)
  2. WFS (work factor systems)
  3. BNTS (basic motion time study)
  4. all of the above
  5. none of the abbvev

Correct answer: (D)
all of the above

70. Process layout is employed for

  1. batch production
  2. continuous type of product
  3. effective utilisation of machines
  4. all of the above
  5. none of the above.

Correct answer: (A)
batch production

Page 7 of 14