141. The technique for establishing and maintaining priorities among the various jobs of any project is known as
Correct answer: (B)
critical ratio scheduling
142. The technique of value analysis can be applied to
Correct answer: (E)
any item.
143. The term 'value' in value engineering refers to
Correct answer: (C)
utility of the product
144. The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as
Correct answer: (C)
free float
145. The time of completing a project in network analysis is given by following time of the critical activity meeting at the finalitiode
Correct answer: (A)
early finish
146. The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as
Correct answer: (E)
Rowan Plan.
147. The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as
Correct answer: (D)
Halsey Premium plan
148. The time which results in the least possible direct cost of an activity is known as
Correct answer: (B)
slow time
149. The two-bin system is concerned with
Correct answer: (A)
ordering procedure
150. The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store
Correct answer: (A)
inflated system