191. The detention period for plain sedimentation water tanks, is usually
Correct answer: (A)
4 to 8 hours
192. The detention time (t) of a settling tank, may be defined as the time required for
Correct answer: (C)
The flow of sewage to fill the tank
193. The detention time of a circular tank of diameter d and water depth H, for receiving the sewage Q per hour, is
Correct answer: (A)
d2 (0.011d + 0.785H)/Q
194. The digested sludge from septic tanks, is removed after a maximum period of
Correct answer: (A)
3 years
195. The dimensions of a rectangular settling tank are: length 24 m, width 6 m and depth 3 m. If 2 hour detention period for tanks is recommended, the rate of flow of sewage per hour, is
Correct answer: (D)
216 cu.m
196. The discharge per unit plan area of a sedimentation tank, is generally called
Correct answer: (D)
All the above
197. The disintegrating pump in which solid matter is broken up before passing out, is
Correct answer: (A)
Centrifugal pump
198. The drainage area of a town is 12 hectares. Its 40% area is hard pavement (K = 0.85), the 40% area is unpaved streets (K = 0.20) and the remaining is wooded areas (K = 0.15). Assuming the time of concentration for the areas as 30 minutes and using the formula Ps = 900/(t + 60) the maximum run off is
Correct answer: (C)
0.15 cumec
199. The drop man holes are generally provided in sewers for
Correct answer: (C)
Hilly town ships
200. The effluent of a septic tank is
Correct answer: (A)
Fit for discharge into any open drain