41. For a given size of bucket, the ideal output of a dragline will be least in
Moist loam
Sand and gravel
Good common earth
Wet sticky clay
Correct answer: (D) Wet sticky clay
42. For completion of a project, the critical path of the network represents
Minimum time
Maximum time
Maximum cost
Minimum cost
Correct answer: (A) Minimum time
43. For excavating utility trenches with precise control of depth, the excavation equipment used is
Hoe
Shovel
Dragline
None of the above
Correct answer: (A) Hoe
44. For the execution of a project, a contractor is
A person
A firm
An agency
All the above
Correct answer: (D) All the above
45. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
1
2
3
4
Correct answer: (A) 1
46. For which of the following materials, the output of power shovels for a fixed shovel size will be maximum
Moist loam
Good common earth
Well blasted rock
Wet sticky clay
Correct answer: (A) Moist loam
47. Frederick W. Taylor introduced a system of working known as
Line organisation
Line and staff organisation
Functional organisation
Effective organisation
Correct answer: (C) Functional organisation
48. Free float for any activity is defined as the difference between
Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and latest start time for its successor activity
Correct answer: (A) Its earliest finish time and earliest start time for its successor activity
49. Free float is mainly used to
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Correct answer: (B) Identify the activities, which can be delayed without affecting the total float of succeeding activity